Concrete quantities: connect the order, delivery and pour record.

Published 24 July 2026Updated 26 September 20267 min read
Theodore Ilori

Published by Darikoda Systems Ltd

Written by Theodore Ilori

Founder. UCL MSc Mechanical Engineering.

When the concrete quantity is questioned, start with the records behind it. Keep delivery tickets, site measurements, returns and transfers connected to the same pour.

On this page

A concrete delivery ticket, an order and a site measurement answer different questions. Connect them to the same pour before comparing the quantities. Record the element, date, deliveries and what happened during placement so the team can investigate a difference later.

Separate the quantities you are comparing

  • Estimated requirement: the volume calculated from the planned dimensions and allowance.
  • Delivered quantity: the supply recorded against the delivery tickets.
  • Site use: the element served, transfers, returns, rejected loads and recorded waste.
Construction workers discussing work on site
Agree who records deliveries, the element served and any return or transfer.

Why the pour record has a commercial job

The buyer sees an order, the supplier sees dispatch tickets and the site team sees the elements being filled. When those references are kept separately, the commercial team has to rebuild the story after the invoice arrives. Recording the movement while the work happens keeps the explanation with the quantity.

A hardened element can still be surveyed and assessed. What is harder to reconstruct is which truck served it, how much went elsewhere, what was returned and why a load waited. Those event details are the reason to keep the record during the pour. They connect the supplier discussion to the site measurement instead of asking either record to answer every question.

Understand yield before calling a delivery short

NRMCA defines yield as the volume of fresh concrete produced from a known batch of materials. Its CIP 8 guidance distinguishes an actual yield discrepancy from an order that does not fill the expected space. Dimensions, form movement, uneven ground and waste can affect the amount needed.

An actual yield check uses batch mass and measured fresh-concrete density. Arrange the appropriate sampling and testing with the responsible technical team. A difference between the order and the drawing quantity alone does not establish a short delivery.

CIP 8 also discusses an ordering allowance of 4 to 10% over plan dimensions for waste and contingencies. That is an allowance when planning supply, not proof that a delivered batch has lost that percentage of yield. Keep the chosen allowance and its reason separate from any later claim of a short delivery.

A worked example: where the delivered concrete went

Consider an illustrative raft with a planned volume of 200 cubic metres and an order of 212 cubic metres. The delivery tickets total 212 cubic metres. The site records 3 cubic metres transferred to a separate footing, 2 cubic metres returned and 2 cubic metres of waste. That leaves 205 cubic metres allocated to the raft: 212 − 3 − 2 − 2 = 205. (Illustrative model, your number from the audit.)

The seven cubic metres outside the raft are accounted for by the transfer, return and waste entries. The five cubic metres between the planned 200 and the allocated 205 still need explaining against the measurement basis and the work. Keep the allocation identifiable as a reconciliation from records. It is not, by itself, a fresh-concrete yield test or an independent survey of the completed raft.

At an illustrative USD 130 per cubic metre, the seven cubic metres represent USD 910 of supplied value to trace. That is not automatically USD 910 lost. The transferred concrete served another element, the return needs checking against the supplier agreement, and the waste needs its own review. Assigning each movement correctly prevents a useful transfer being presented as unexplained loss. (Illustrative model, your number from the audit.)

Use the same references in the cost review. The footing should carry the transferred quantity, the raft should retain its own allocation and the return should remain open until its treatment is agreed. A project total can balance while the costs of two individual elements are still wrong.

Record each delivery against the pour

  • Ticket, truck, supplier and mix reference.
  • Arrival and discharge times.
  • Element or work area receiving the load.
  • Recorded checks and supporting test references.
  • Returns, rejected loads, transfers and waste.
  • Person recording the entry and the follow-up review.
Site professional inspecting building works with a tablet
Keep site measurements and delivery records connected to the same element.

Use consistent units and keep the source of each quantity visible. Where a figure is estimated, record the basis used. This lets the reviewer compare like with like instead of treating every number as a direct measurement.

Give each stage a recording owner

  • Before ordering, record the element reference, drawing revision, measured or planned dimensions and allowance used.
  • At arrival, connect the truck and ticket to the order, record the time and identify the person receiving the load.
  • During discharge, record the element served and any change of destination against the same ticket.
  • If a load is rejected or returned, record the quantity basis, reason, instruction and supplier reference.
  • After placement, review the deliveries, movements, tests and site measurements together, with an owner for unresolved entries.

A pump serving more than one element needs an explicit change of destination in the record. If a remaining load is used on a footing to keep work moving, record the transfer on both elements. The decision can be operationally useful and still leave a cost gap if only the original destination appears on the ticket.

Plan for delivery conditions on Ghana sites

NRMCA's hot-weather guidance explains that high concrete temperature accelerates slump loss and setting, while heat, wind and low humidity affect moisture loss. For a hot-weather pour, keep arrival, waiting and discharge times with the test and acceptance records agreed by the technical team.

Use the delivery route and expected travel time when arranging the pour with the supplier. Check that the receiving crew, pump and work area are ready. If delivery is delayed or the sequence changes, record the instruction and revised destination rather than leaving the ticket to imply that the original plan happened.

When a load is questioned, retain the acceptance or rejection decision and its supporting test reference. This gives the supplier and site team a specific event to review. The commercial treatment of waiting, returns or part-loads should follow the agreed supply terms, with the relevant records available to both sides.

Keep the payment review connected

The commercial team needs the relevant site measurements and supporting records when preparing a payment claim. Keep queried quantities and the outcome of their review alongside the original entry. The contract and agreed measurement basis guide that review.

Keep the supply review and the payment measurement connected without treating them as the same quantity. An invoice concerns the supply terms. A payment application concerns the work valued under the construction contract. The commercial team needs both the delivery trail and the appropriate measurement, with queries carried forward until resolved.

The guide to queried hours and quantities follows a measurement difference through the review. Use that process when the submitted and reviewed amounts differ, keeping the reason for each adjustment visible.

Make the next pour easier to review

Use what the team learns to improve the next order and recording process. A clear reason for a difference is more useful than one unexplained total across the whole project.

Frequently asked questions

What is concrete yield?
Yield is the volume of fresh concrete produced from a known batch of materials. Batch mass and measured fresh-concrete density are used to evaluate it.
Does using more concrete than estimated prove a short delivery?
No. Review the measurement basis, site conditions, deliveries, transfers, returns and waste, with appropriate testing where yield is in question.
Can concrete quantities be assessed after the pour?
Yes. The completed work can be surveyed and assessed. A record made during the pour also preserves delivery timing, returns, transfers and test references that are harder to reconstruct later.
Is an ordering allowance the same as a yield loss?
No. An allowance helps plan the quantity to order for the work and contingencies. Yield is evaluated using batch quantities and measured fresh-concrete density. Keep those two calculations separate.
What should happen when concrete moves to another element?
Record the source delivery, quantity basis, original element, receiving element and person confirming the move. Assign the movement to both records so the quantities and costs can be reviewed together.
Why record the pour while it happens?
Delivery timing, transfers, returns and the people involved are easier to record accurately during the work. Keep those details connected for later review.
How does Darikoda help with the record?
Darikoda connects site entries, supporting photos and review details to the project and work area, helping the team find the information behind a reported quantity.

Review the records behind one pour

Use the free 30-minute audit to follow a delivery through to the work record and commercial review. Leave with a one-page map of the practical gaps and priorities for your project.

ConstructionConcreteReady-mixCost integrity

Want this analysis applied to your own operation?

Pick a 30-minute window or message us on WhatsApp. You walk away with a one-page leakage map specific to your fleet.

← Back to all Operating Guides

Operating Guides draw on extensive field audits and industry research across Ghana's mining, construction, roadworks, and quarry sectors. No specific operator is named or identifiable. External sources are cited inline where regulatory or commercial reference is made.